CB&A Project Management
Construction Estimating Training Manual
1.Introduction to Construction Estimating
What is Estimating?
Estimating is the systematic process of predicting the cost
required to complete a project within a defined scope, schedule, and quality
level.
Why Estimating Matters
Determines project feasibility, supports bid competitiveness, establishes a baseline budget, enables cost control and forecasting, and forms the basis for contract negotiation.
Types of Estimates
Estimate Type | Accuracy Range | Project Phase |
Conceptual / ROM | -30% to +50% | Early planning |
Budget Estimate | -15% to +25% | Preliminary design |
Definitive Estimate | -5% to +10% | Final design |
Bid Estimate | Competitive | Tender stage |
2. Estimating Process Overview
Step-by-Step Workflow
- Scope Review
- Drawing & Specification Review
- Quantity Takeoff
- Labor Productivity Analysis
- Material Pricing
- Equipment Costing
- Subcontractor Quotations
- Indirect Costs
- Risk & Contingency
- Markup & Profit
3. Quantity Takeoff Fundamentals
Manual Takeoff
- Scale drawings
- Highlight & color code by discipline
- Use standardized measurement sheets
Digital Takeoff Tools
- On-Screen Takeoff
- Bluebeam
- PlanSwift
Example Calculation
Concrete Slab:Length × Width × Thickness
100 ft × 50 ft × 0.5 ft = 2,500 cubic feet
Convert to cubic yards = 92.6 CY
Direct Cost Components
Labor Costs
Labor Hours = Quantity × Productivity Rate
Labor Cost = Labor Hours × Hourly Rate
Factors:
- Crew composition
- Overtime
- Learning curve
- Site conditions
Material Costs
- Vendor quotes
- Freight
- Taxes
- Escalation
Equipment Costs
- Owned equipment rate
- Rental rates
- Fuel & maintenance
- Mobilization
4. Indirect Costs & Overhead
Includes:
- Site supervision
- Temporary facilities
- Safety program
- QA/QC
- Permits
- Insurance
- Bonds
6. Contingency & Risk
Types of Risk
- Scope gaps
- Design development
- Market volatility
- Weather
- Labor shortages
Contingency Approaches
- Percentage-based
- Risk register driven
- Monte Carlo simulation (advanced)
7. Markup & Pricing Strategy
Final Price = Direct Cost
- Indirect Cost
- Contingency
- Overhead
- Profit
Consider:
- Market competition
- Client relationship
- Risk appetite
- Strategic positioning
8. Estimating Software Overview
Primavera P6
Used for:
- Time-phased budgeting
- Cost loading
- Earned value integration
WinEst
Used for:
- Detailed assemblies
- Cost databases
- Historical cost tracking
Microsoft Excel
Used for:
- Custom models
- Bid comparison
- What-if analysis
9. Integration with Project Controls
Estimating feeds:
Discipline | Integration Point |
Scheduling | Duration assumptions |
Cost Control | Budget baseline |
Procurement | Commitment tracking |
Risk Management | Quantified exposure |
Earned Value | BCWS baseline |
Strong estimators:
- Understand schedule logic
- Validate productivity assumptions
- Support change order pricing
- Assist claims analysis
Estimating Case Study Exercise
Scenario:
Industrial building – 50,000 SF
Disciplines:
- Sitework
- Concrete
- Structural Steel
- MEP
Participants must:
- Perform quantity takeoff
- Apply productivity rates
- Calculate labor & material
- Apply overhead and profit
- Present bid summary
